Saturday, November 19, 2016

Autumn progress at Cae Helygen

No update in the last few months but we have made progress-
Electricity supply installed
Bedrooms concrete floor laid
Blockwork walls to make the bedrooms and bathroom
Sewage treatment plant installed
Currently we have installed the crogloft floor beams and are putting the joists in and the roof slates are coming along.......
 Hardcore and sand blinding on the bedrooms floor  with thickening for the blockwork walls. Visqueen next
 Concrete mixer arrived 
 Barrowing the concrete in

 Jonny - Tim and Liz making a proper tamping device
 Liz and Jonny borrowing
 Alan, Jonny Tim, Liz and Chris  a great job thanks 
 The walls in the bedrooms area were not square so it was challenging to work out what to do then Dan came back and blocked up the walls.
 Dan did a great job - I finished off the walls with the raking tool 

Nearly ready for the crogloft steels
 Robyn came back and dug the trench for the electricity supply
 Scottish power came and joined it all up- good job
 We ordered 2 crogloft steels - pretty heavy and used the JCB to move them in through the gable end
 Steve the stone mason and Tim helped to move the steel into place- we bought wheels for the scaffolding which make a huge difference to moving it around
 Robin came back and dug the hole for the Sewage treatment plant  which is a Marsh industries 4-6 person packet treatment plant
 Concreting the base
 In place and inspection chambers being fitted

  Getting the fall right was important across the yard 25mm per metre. it was shallow across the yard so we covered it with mesh and concrete 


Monday, August 22, 2016

Concreting the living room floor

The next job was to concrete the living room floor.
We ordered 20 tons of MOT 1 sub floor and laid it out and whacked it down. We used the laser level to get the levels right.  John and James helped to sort this  out- 100 wheelbarrows of sub base.
We laid the visqueen on a bed of sand and then ordered nearly 5 cubes of concrete to provide a 100mm  floor.
John, Jonny, Jen and me did the job, concrete form Porthmadog concrete. We were probably one person short, but we will managed.  Two barrow wheels got punctures which didn't help!
Tamping was hard work and maybe we needed to think of a better tamping method.
The lorry driver gave us 8/10 which was heartening.
 20 tons of hardcore
 Getting to floor level- hard work
 We used a big plank, level and laser lever then whacked it flat
 Visqueen laid on a bed of sand
 Jen cutting the visqueen
 Concrete arrives

Barrowing, raking and tamping - Jonny the tamper 
John the barrow man 

 
      Another job done

Stone Masons

Steve and Steve the stone masons from Anglesey have started to build the courtyard and built the pillars at the entrance the main room doorway.
They are pretty skilful guys who know how to manhandle and carefully place stone.
A lot of sand and cement was used.

Entrance to barn, gable frame ready to be stone clad




Stone retaining wall being built



The right pillar
This small wall will be topped with slate and used for seating BBQ's etc

Stone wall art





Pillar on the left and digging out the  living room floor

View of the wall through the doorway





Saturday, June 11, 2016

Stone Facing the Kitchen

Steve and Steve from Anglesey recommended by our JCB driver Robyn have been stone facing the kitchen using random rubble from our pile of stone.
They are rock artists- very skilful indeed.







 One of the Steve and Steve's
 Wide slate window ledges from Blaenau Ffestiniog



 The sides of the gable frame will have mini buttresses 


 There is a rabbit in this wall can you see it?
 Before and after such a difference